Utility Shutdowns

Latest Utility Shutdowns for 2013:

From 8 am on Monday, April 22 through
5 pm on Friday, May 31.

Environmental Studies (ES) - FM will begin the replacement of the ES Heat Exchanger Monday April 22, 2013 and expects the project to be completed by May 31, 2013. This will mean a majority of the building heating system will not be functional during this project. Due to scheduling and budget constraints we are unable to wait for warmer weather to perform this critical work. This may mean cool temperatures inside ES depending upon the outside temperatures.

ES Heat Shutdown: Construction Update for 5/14/13ES Heat Shutdown: Construction Update for 5/14/13
The heat exchanger project is staying on schedule and we are moving closer to completion. As you can see in the picture, work is progressing and the future is looking warm.


We sincerely appreciate the flexibility and patience you have all demonstrated during this project.

Please address any questions or concerns to
FM Work Control Center at x3420.


From 8 am on Monday, May 20 through
5 pm on Friday, May 24.

Environmental Studies (ES) - Beginning Monday May 20, 2013 the Carpenter Shop will start installing the new Mecha Roller Shades for ES on the 1st, 2nd and 3rd floors. The specific rooms are highlighted on the floor plans below. Classroom work will be scheduled when no classes are in session in the room(s). The Carpenters try to make contact when possible with the occupants of private offices prior to the work being performed. The work will take approximately one hour per shade so if you have 3 windows in your office you can anticipate about 3 hours of work. There is noise associated with the drilling of the holes for the shade mounts, but this is of short duration and we will do what we can to minimize any impact this may have.

Environmental Studies 1st, 2nd, and 3rd Floors New Window Shades

Thank you for your patience and understanding during this project.

Please address any questions or concerns to
Craig Evans Carpenter Shop Supervisor at x3218.


Scheduled System Shutdowns:
To shut down any major system, submit a "Request for Notification/ Shutdown Form" to the Work Control Center 21 days prior to the requested shut down. This allows adequate time for the Work Control Center to notify all occupants and concerned parties prior to shutdown.

Emergency Shutdowns:
During the course of ordinary maintenance and construction, emergency shutdowns will occur. The Work Control Center will notify occupants and concerned parties.

For more information about scheduled or emergency utility shutdowns contact the Work Control Center at 650-3420.

 

Steam Plant

Page Updated 05.17.2013