2013-2015 Legislative Appropriations and Reappropriations

North Campus Utilities Upgrades

(Project ID 30000426)

Fund Code Source Prior Expenses Reapprops New Approps
057 State     3,462,000
065 Local     120,000
TOTAL FUNDS: $3,582,000

The North Campus Utility Upgrade project upgrades the existing north campus 4,160 volt electrical distribution system to a looped 12,470 volt system pursuant to the 2001 Utilities Master Plan. The existing distribution system is a radial feel network and failure in a critical location could cause an outage that lasts days instead of hours for the affected buildings. Buildings connected to the north campus system are Old Main, Mathes Hall, Nash Hall, Higginson Hall and Edens Halls (both North and South).

2013-2015 FUNDING: $3,582,000